Dáil Question on completion of Celbridge Community College – 11th November 2015

Uimhir:144 Ceist Pharlaiminte
Chun an Aire Oideachais agus Eolaíoctha
To the Minister for Education and Science

To ask the Minister for Education and Skills the timeline for the completion of
the Celbridge Community College in County Kildare; and if she will make a
statement on the matter.
– Anthony Lawlor.

* For WRITTEN answer on Wednesday, 11th November, 2015.
Reference Number: 39694/15

Freagra
Minister Jan O’Sullivan

An unsuccessful planning application including an appeal have delayed
progression of the Celbridge Community College.

Discussions are ongoing with the local authority to resolve the contentious
issues. Pending finalisation of these matters unfortunately I am unable to
provide a timeline for completion of the project.